0928_huon_0530928_huon_0550928_huon_058

National Arboretum Canberra

Other

  • Project completion date:February 2015
  • Overall value of project:$1.3m
  • Location:National Arboretum Canberra
  • Client:ACT Procurement & Capital Works

The project included construction of a seven megalitres dam with revetment mattresses stabilised spillway, 1.7km mainline pipe which transfers water from the new dam to the underground storage tank on Dairy Farmer’s Hill and  installation of three filtration units, three pumps, an injection unit and stations to house this equipment.